Two formats of preparing a progress claim are Full Trade Brake up and pre-determined staged payments.
The Full Trade Break-ups are prepared while stating each and every trade’s value involved in the tender. The example is as given in the Full Trade Break-up provided above.
Then, with the job’s progress, claims are made based on the value percentage of completed work at each trade by the time of presenting the claim. This is done as in the example below:
TRADE
|
VALUE
|
PERCENTAGE
COMPLETE
|
COMPLETE CLAIM VALUE
|
Structural Steel
|
$54,000
|
45%
|
$24,300
|
Excavation Expenses
|
$23,450
|
75%
|
$17,587.50
|
Roofer
|
$5,500
|
100%
|
$5,500
|
Painter
|
$24,000
|
40%
|
$9,600
|
Landscaper
|
$74,000
|
48%
|
$35,520
|
Site Works
|
$1,454
|
78%
|
$1,134.12
|
Concreter
|
$110,450
|
80%
|
$88,360
|
Preliminaries
|
$202,854
|
78%
|
$158,226.12
|
13 February 2011
Contract Reference: GRT764
Giovanna & Sons Holdings Ltd.
35454-001 Millennium Street
Southern State
RE: JOB NO. 879
PROGREES CLAIM NO. 4
|
Debit
|
Credit
|
CONTRACT PRICE VALUE $ 900,000
|
|
|
Works Completed to Date (0.45*900,000)
|
405,000.00
|
|
Less Amount of Money Received to Date
|
|
250,000
|
Variation No.1 Kitchen
Variation No.2 Extended Verandah
Variation No 3.Extended Water Shelter
|
2,540
2,000
|
3,400
|
SUB TOTAL
|
$ 409,540
|
$ 253,400
|
|
|
|
PROGRESS CLAIM NO. 4
|
$ 156,140
|
|
REVISED CONTRACT SUMMARY
|
Debit
|
Credit
|
CONTARCT PRICE VALUE
|
$900,000
|
|
Variation No.1 Kitchen
Variation No.2 Extended Verandah
Variation No 3.Extended Water Shelter
|
2,540
2,000
|
3,400
|
SUB TOTAL
|
904,540
|
3,400
|
|
|
|
REVISED CONTRACT PRICE VALUE
|
$ 901,140
|
|
PART B: (I)
RE: JOB NO. 7686
PROGREES CLAIM NO. 4
|
Debit
|
Credit
|
CONTRACT PRICE VALUE $ 900,000
|
|
|
Works Completed to Date (0.45*900,000)
|
405,000.00
|
|
Less Amount of Money Received to Date
|
|
250,000
|
Variation No.1 Kitchen
Variation No. 2 Extended Verandah
Variation No. 3 Water Shelter
Variation No. 4 Tiles Fixing
|
2,540
2,000
|
3,400
8,800
|
SUB TOTAL
|
$ 409,540
|
$ 262,200
|
|
|
|
PROGRESS CLAIM NO. 4
|
$ 147,340
|
|
Part B: (II)
The procedure for lodging a claim:
First is to identify who received the variation advice, then state the scope of the work in the variation advice, elaborate how the Variation Advice is to be completed, identify if an extension of time is require or not, and if so, document it, cost the variation as per the table below, submit the variation, and eventually, the variation is received and approved.
13 February, 2011
Contract Reference: GRT764
Giovanna & Sons Holdings Ltd
35454-001 Millennium Street
Southern State
VARIATION PRICE REQUEST NO. 6
GIOVANNA & SONS HOLDING, UNITS
Don't wait until tomorrow!
You can use our chat service now for more immediate answers. Contact us anytime to discuss the details of the order
DESCRPTION OF
WORKS
The Owner of the Construction requested for an additional service which involved the Carpeting of the two units, i.e. the two storeys plus the garage.