The G&E Company is preparing a bid to build the new 47,000 seat Pilots’ baseball stadium. The construction must start on July 1, 2011, and be completed in time for the start for the 2014 season. A penalty clause of $100,000 per day of delay beyond May20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said the prospects for future projects are quite good since there is a projected renaissance in building ball parks with modern luxury boxes.

Given the information provided in the Case Appendix, construct a network schedule for the stadium project and answer the following questions:

Will the project be able to be completed by the May20 deadline? How long will it take?

The project will be complete by 10 March 2014. This is within the deadline. The project will finish before 20 May 2014. The project will

What is the critical path for the project?

The critical path is 10 March 2014 when the project will be completed.

Based on the schedule would you recommend that G&E pursue this contract? Why? Include a one page Gantt chart for the stadium schedule

 G & E should go ahead with the project, as there will be no time constraints. They have enough time to undertake the other projects.

The baseball stadium is an outdoor structure with a retractable roof. The project begins with clearing the site, an activity that lasts 70 days. Once the site is clear, work can start simultaneously on the structure itself and demolishing an adjacent building site. This demolition is necessary to create a construction stage for storing materials and equipment. It will take 30 days to demolish the buildings and another 70 days to set up the construction site.

Don't wait until tomorrow!

You can use our chat service now for more immediate answers. Contact us anytime to discuss the details of the order

Place an order

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl (120 days) can occur.

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).

The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

  The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

  If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

  The construction crew work Monday through Friday.

Calculate the Price of Your Paper

 
300 words
-+
 

Related essays

  1. Personnel Management
  2. Various Management Theories
  3. Designing and Managing the Supply Chain
  4. Leadership versus Management
Discount applied successfully